Document Types
Document types used in this project.
Document types used in this project.
CFIHOS-70000176
A report issued to achieve timely notification report of any accident incident occurring during the projects, including on-site, in contractors offices, etc. Severity requirements to be specified by 'owner/operator'.
CFIHOS-70000177
An assessment which is generated by 3rd party technical or execution expert on work done in their relevant field to assess correctness of approach/deliverable.
CFIHOS-70000178
Books, as defined in the CFIHOS require this Index to be created. Since the purpose of the 'index' is management of a group of documents, this can only be associated with JA 'information management'. Examples: 'health', 'safety', 'environment', 'quality communication dossier basic design', 'engineering package authority approval package'.
CFIHOS-70000097
Specification of the Information types required by the owner for delivery and handover.
CFIHOS-70000179
An authoritative collection of values with a relationship to a specific equipment. List to show input and output of an equipment (e.g. instrument, telecom equipment) connected to other equipment (e.g. distributed control system, programmable logic controller).The columns of this collection is specified and controlled.
CFIHOS-70000180
A document capturing what particular activities and requirements will be executed and delivered relating to inspection and testing for construction & vendor work.
CFIHOS-70000442
A document confirming completion or waiver of final equipment inspection by the purchaser or purchaser representative.
CFIHOS-70000245
A report documenting status and observations relating to an asset/object. Can include paint, insulation, noise, thickness measurement, destructive weld testing, NDE, preservation, cathodic protection tests, etc. Excludes pressure tests.
CFIHOS-70000425
A report documenting assumptions and method determining acceptable loading conditions prior to operation, including but not limited to load out, transport, and installation for handling and assembly. Intended to support handling/installation guidance to project team(s).
CFIHOS-70000119
Installation refers to the mounting, setting, erection, etc. of equipment and accessories. These diagrams are for transient activity during installation (eg. sequence of activity) and not finished work.
CFIHOS-70000181
A document that describes methods of installing a piece of equipment. Installation refers to the mounting, setting, erection, etc.
CFIHOS-70000418
An authoritative collection of values with a relationship to instrumentation. The columns of this collection is specified and controlled.
CFIHOS-70000411
A diagram detailing insulation, including anchoring and expansion joints, etc. Includes refractory.
CFIHOS-70000443
A document describing details of an interface between contract scopes including responsibilities, execution, deliverables, and actions.
CFIHOS-70000186
A diagrams documenting Interfaces and demarcation of responsibilities between different organizations (e.g. battery limits, terminations).
CFIHOS-70000188
A document capturing what particular activities and requirements will be executed and delivered to manage interface between internal and external parties (esp. between contract scopes).
CFIHOS-70000189
A procedures around Interface management activities between internal and external parties.
CFIHOS-70000190
A register documenting agreements and responsibilities between internal and external parties (esp. between contract scopes).
CFIHOS-70000419
A list of interlocks that automatically bring process to a safe state in response to specific initiating events.
CFIHOS-70000191
A standardised document by which the Company invites Tenderers to submit a tender for a Contract. It encloses the conditions for the submission of a tender and gives the terms of reference or the technical qualifications required.
CFIHOS-70000192
A document outlining the premise and intent for isolation philosophy for safe plant operation and maintenance.
CFIHOS-70000193
Construction detail diagram for 'piping and ducting', providing an accurate 'bill of materials' (BOM) / 'material take off' (MTO) and represented in a 3 dimensional isometric view.
CFIHOS-70000196
A plan view diagram of a plant/group of plants showing the interfaces of layout diagrams of components. Typically only shows major equipment and infrastructure to provide context and orientation.
CFIHOS-70000277
A diagram showing the precise location of assets/objects at a plant, process unit, or area basis relative to surrounding structures and equipment.
CFIHOS-70000197
A report which documents lessons gained from the execution of the project.