Document Types

Document types used in this project.

  • capital spares study

    CFIHOS-70000037

    A consolidated study reviewing critical equipment and recommending capital spares.

  • A diagram showing locations of cathodic protection and schematic diagrams.

  • A diagram that is showing the causes and consequences of different errors, especially related to failures in the control system.

  • A procedure describing how changes through 'design', 'construction' and 'commissioning' will be managed.

  • A consolidated register of proposed and/or processed change associated with all change to originally agreed design scope/statement of requirements, including basis for design.

  • change notification

    CFIHOS-70000044

    An advance notice to another party, e.g. another design department or fabrication facility, that there is going to be a change to a document that has been issued for construction.

  • change order

    CFIHOS-70000347

    A notification formally incorporating the change issued against existing 'contracts', 'agreements' and/or 'purchase orders' based on a change request.

  • change proposal

    CFIHOS-70000395

    A document which captures a recommended course of action with justifications from technical and/or commercial aspects to execute an activity to change something. May lead to a change request.

  • change request

    CFIHOS-70000349

    A request, approval or rejection of changes to an existing contract. Would typically include justification and reasons for the request, and acceptance or rejection from a commercial or contractual perspective, but may also contain some technical content. For similar documents pertaining specifically to technical deviations, with no commercial/contractual content, refer to 'technical deviation request'. May be triggered by a change proposal.

  • check sheet

    CFIHOS-70000417

    A collection of specific activities to test completeness of installation or energization of a specific equipment class. Includes collection of specific data based on testing parameters.

  • Detailed report from results of corrosion inhibition, hydrates, flow assurance, etc testing plan. Includes any preliminary testing required to establish parameters for testing.

  • chemical testing plan

    CFIHOS-70000074

    A document capturing parameters and requirements to validate selection of chemicals including but not limited to corrosion inhibitors, hydrate inhibitors, and flow assurance chemicals.

  • clarification request

    CFIHOS-70000045

    Request (e.g., from a Contractor) for clarification of scope, technical details, or assumptions.

  • A document outlining purpose and approach for commissioning and start-up.

  • A cross-discipline, internal and external communication procedure, responsibilities, and governance.

  • completion certificate

    CFIHOS-70000414

    A document certifying a scope or project activity has been successfully completed and tested for functionality.

  • connection diagram

    CFIHOS-70000055

    A diagram showing details of cable numbers and terminations point to point (e.g., to/from vendor packages, equipment).

  • A consolidated spare parts list generated to support execution of project purchasing for the purpose of commissioning, start-up, maintenance support, etc.

  • constructability study

    CFIHOS-70000062

    A document assessing sequence and method of construction of a facility to determine the best way to proceed.

  • construction diagram

    CFIHOS-70000057

    A diagram detailing assembly and fabrication.

  • construction schedule

    CFIHOS-70000060

    A time-based document outlining sequence and duration of activities related to the completion of construction scope. Construction includes site erection and assembly but not fabrication at third party sites.

  • contract

    CFIHOS-70000063

    A binding document which records a agreement and its related mutual obligations and commitments. Typically having effect on a project or the future life of a facility. For example a sales contract, maintenance contract, etc.

  • control philosophy

    CFIHOS-70000064

    A document outlining the premise and intent for start-up and shutdown for process control. May also list instrument and control equipment, pre-alarm and shutdown alarm/trip requirements, failure modes of valves and equipment and type of signals to and from the control logic. Basis to develop more detailed control narrative.

  • control system diagram

    CFIHOS-70000066

    A pictorial representation of the main elements and functions of a control circuit/system with input/output sources (switches, relays etc.) and their relationships. Details logic functions of the circuit/system. I/O loading and cabinet layouts.

  • A report detailing actions to be taken to improve a process resulting from an 'audit' or 'quality assessment'.